Salient Features of The project

GENERAL

 
Name of the Project Super Madi Hydroelectric Project 
Developer Super Madi Hydropower Ltd. 
Name of the River Madi River 
Type of Scheme  Run-of-River
Project Location  Madi Rural Municipality 
District Kaski
Province Gandaki Province 
Latitude 28°19’ 02” N to 28°21’ 39” N
Longitude 84° 04’ 45” E to 84° 08’ 34” E
Nearest Town  Pokhara
Gross Head  295.97 m
Rated Net Head 280.67 m
Normal Operating Headwater Level  1344.00m amsl 
Tailrace water level  1048.03 m amsl 
WEIR   
Weir Crest Level  1344.00m amsl 
Type of Weir Free flow concrete ogee weir 
Length of overflow weir  37.90 m
Lowest River Bed Level at Weir Axis  1335.00 m amsl
100 Years Flood 1508 m3/s
INTAKE  
Catchment Area at Intake site 278.136 km2
Design Flow 18.00 m3/s
Riparian Release 1.521 m3/s
Intake Type Side intake
Intake orifice number/size 4 Nos./ 3.6 m wide x 2.0 m high
UNDERSLUICE  
No., Dimension (length x breadth) Under-sluice  2 nos., 4.0 x 4.0 m 
Invert level at gate EL 1336.00 m amsl
GRAVEL TRAP  
Length (effective)  17.0 m
Width 9 m
Height 10.4 m
Particle Size to settle ≥5 mm (at 85% efficiency)
UNDERGROUND SETTLING BASIN  
Type Flushing Type
Settling Criteria  90%, ≥ 0.20 mm
Number of Chambers 2
Inlet Transition Length (m) 28.0m
Settling Basin Size (uniform section)  124 m long x 12.30 m wide and 21.90 m high each
Outlet Transition Length (m) 15.0m
Flushing System Intermittent
Size of Flushing Channel 1.00 m x 1.5 m (B x H), slope 1:50,1:24
Approach tunnels to settling basins length 111.64m
Inspection tunnel to settling basins length 224.65m
Inspection tunnel portal level (excavation) 1335.29 m amsl
Headrace Tunnel (HRT)  
Type of Flow  Low Pressure Tunnel
Shape of Tunnel Inverted U
Length (excluding settling basin, adits, Inspection tunnel, flushing tunnels, Kalbandi Kholsi crossing, approach tunnel and tunnel stretch before vertical drop, surge shaft connecting tunnel) 5282.31 m
Length from settling basin outlet to vertical drop 153.66 m
Excavation Size without pay line 4.2 m x 4.2 m (B x H)
Support Type Concrete/ Shotcrete/Rock bolt
Tunnel inlet portal invert level before settling basin (finish) 1337.00 m amsl
No. of Intermediate Adits for HRT 2
Surge Shaft  
Type Cylindrical
Diameter (finished) 8m
Height  81.20 m
Bottom Level EL 1287.00 m amsl
Length of Connecting tunnel 46.25 m
Connecting tunnel meeting point invert level with HRT EL 1284.93 m amsl
Penstock Pipe  
Type Exposed steel lined 
Length 1401 m of 2.70 m dia., 23.13 m of 2.20 m dia. and 211.86 m of 1.60 m dia.
Diameter/Thickness  2.70 m dia. / 12-50 mm thick, 2.2 m dia. / 45 mm    thick , 1.6 m dia. / 36 mm thick for E-350 Steel
Powerhouse  
PH dimension (L X B X H) 46.00 x 16.0 m x 28.4m
Turbine Axis Level EI 1045.65 m amsl
PH Access Floor Level EL 1052.90 m amsl
Tailrace  
Type  Concrete box culvert
Size 3.2 m x 3.0 m (B x H)
Length of Tailrace 195 m
Slope 1 in 500
Invert Level of Tailrace outlet 1045.43 m amsl
Turbine  
Type Vertical Axis Francis Turbine
Number of Units 3 (Three)
Rated Capacity per Unit + 10% COL  15.28 MW
Discharge per Unit 6.0 m3/s
Turbine Axis Elevation 1045.65 m amsl
Tail water level 1048.03 m amsl
Turbine efficiency 90 %
Generator  
Type of Generators  Three phase, Synchronous, Static
Number of Unit 3 (Three)
Rated Output+ 10 % COL  17260 kVA
Generation Voltage  11.0 kV 
Frequency 50 Hz 
Power Factor 0.85
Generator efficiency 97 %
Transformers  
Type Three Phase, Oil immersed
Number of Units  3
Frequency  50 Hz
Transformer Efficiency  99.0%
Rated capacity per unit  17,500 kVA
Primary (LV Side) 11 kV
Secondary (HV Side) 132 kV
Transmission Line  
Transmission Voltage (kV) 132 kV
Length (km) upto Upper Madi Powerhouse 7 km
Length (km) from Upper Madi Powerhouse to Lekhnath S/S 10.5 km 
Type of Circuit Single Circuit upto Upper Madi HP and Double circuit from Upper Madi HP to Lekhnath S/S
Line Conductor ACSR (Bear)
Proposed Interconnection Point 132 kV NEA Substation at Lekhnath
Power and Energy   
Installed Capacity 44 MW
Deemed / Contract Energy  242.65 GWh 
Wet Saleable Energy 204.894 GWh
Dry Saleable Energy 37.756 GWh
Construction Time and Key Dates  
Development and Construction Time Period 1 year (access road) + 3 years
Purchase Agreement with NEA  February 09, 2017 (Magh 27, 2073)
Generation License Issued Date and Validity March 30, 2017 (Chaitra 17, 2073) 35 years
Required Commercial Operation Date (RCOD) June 11, 2021 (Jestha 28, 2078)
Revised RCOD  August 16, 2023 (Bhadra 1, 2079)