Salient Features of The project

GENERAL

 
Name of the ProjectSuper Madi Hydroelectric Project 
DeveloperSuper Madi Hydropower Ltd. 
Name of the RiverMadi River 
Type of Scheme Run-of-River
Project Location Madi Rural Municipality 
DistrictKaski
ProvinceGandaki Province 
Latitude28°19’ 02” N to 28°21’ 39” N
Longitude84° 04’ 45” E to 84° 08’ 34” E
Nearest Town Pokhara
Gross Head 295.97 m
Rated Net Head280.67 m
Normal Operating Headwater Level 1344.00m amsl 
Tailrace water level 1048.03 m amsl 
WEIR  
Weir Crest Level 1344.00m amsl 
Type of WeirFree flow concrete ogee weir 
Length of overflow weir 37.90 m
Lowest River Bed Level at Weir Axis 1335.00 m amsl
100 Years Flood1508 m3/s
INTAKE 
Catchment Area at Intake site278.136 km2
Design Flow18.00 m3/s
Riparian Release1.521 m3/s
Intake TypeSide intake
Intake orifice number/size4 Nos./ 3.6 m wide x 2.0 m high
UNDERSLUICE 
No., Dimension (length x breadth) Under-sluice 2 nos., 4.0 x 4.0 m 
Invert level at gateEL 1336.00 m amsl
GRAVEL TRAP 
Length (effective) 17.0 m
Width9 m
Height10.4 m
Particle Size to settle≥5 mm (at 85% efficiency)
UNDERGROUND SETTLING BASIN 
TypeFlushing Type
Settling Criteria 90%, ≥ 0.20 mm
Number of Chambers2
Inlet Transition Length (m)28.0m
Settling Basin Size (uniform section) 124 m long x 12.30 m wide and 21.90 m high each
Outlet Transition Length (m)15.0m
Flushing SystemIntermittent
Size of Flushing Channel1.00 m x 1.5 m (B x H), slope 1:50,1:24
Approach tunnels to settling basins length111.64m
Inspection tunnel to settling basins length224.65m
Inspection tunnel portal level (excavation)1335.29 m amsl
Headrace Tunnel (HRT) 
Type of Flow Low Pressure Tunnel
Shape of TunnelInverted U
Length (excluding settling basin, adits, Inspection tunnel, flushing tunnels, Kalbandi Kholsi crossing, approach tunnel and tunnel stretch before vertical drop, surge shaft connecting tunnel)5282.31 m
Length from settling basin outlet to vertical drop153.66 m
Excavation Size without pay line4.2 m x 4.2 m (B x H)
Support TypeConcrete/ Shotcrete/Rock bolt
Tunnel inlet portal invert level before settling basin (finish)1337.00 m amsl
No. of Intermediate Adits for HRT2
Surge Shaft 
TypeCylindrical
Diameter (finished)8m
Height 81.20 m
Bottom LevelEL 1287.00 m amsl
Length of Connecting tunnel46.25 m
Connecting tunnel meeting point invert level with HRTEL 1284.93 m amsl
Penstock Pipe 
TypeExposed steel lined 
Length1401 m of 2.70 m dia., 23.13 m of 2.20 m dia. and 211.86 m of 1.60 m dia.
Diameter/Thickness 2.70 m dia. / 12-50 mm thick, 2.2 m dia. / 45 mm    thick , 1.6 m dia. / 36 mm thick for E-350 Steel
Powerhouse 
PH dimension (L X B X H)46.00 x 16.0 m x 28.4m
Turbine Axis LevelEI 1045.65 m amsl
PH Access Floor LevelEL 1052.90 m amsl
Tailrace 
Type Concrete box culvert
Size3.2 m x 3.0 m (B x H)
Length of Tailrace195 m
Slope1 in 500
Invert Level of Tailrace outlet1045.43 m amsl
Turbine 
TypeVertical Axis Francis Turbine
Number of Units3 (Three)
Rated Capacity per Unit + 10% COL 15.28 MW
Discharge per Unit6.0 m3/s
Turbine Axis Elevation1045.65 m amsl
Tail water level1048.03 m amsl
Turbine efficiency90 %
Generator 
Type of Generators Three phase, Synchronous, Static
Number of Unit3 (Three)
Rated Output+ 10 % COL 17260 kVA
Generation Voltage 11.0 kV 
Frequency50 Hz 
Power Factor0.85
Generator efficiency97 %
Transformers 
TypeThree Phase, Oil immersed
Number of Units 3
Frequency 50 Hz
Transformer Efficiency 99.0%
Rated capacity per unit 17,500 kVA
Primary (LV Side)11 kV
Secondary (HV Side)132 kV
Transmission Line 
Transmission Voltage (kV)132 kV
Length (km) upto Upper Madi Powerho7 km
Length (km) from Upper Madi Powerhouse to Lekhnath S/S10.5 km 
Type of CircuitSingle Circuit upto Upper Madi HP and Double circtuit from Upper Madi HP to Lekhnath S/S
Line ConductoACSR (Bear)
Proposed Interconnection Point132 kV NEA Substation at Lekhnath
Power and Energy  
Installed Capacity44 MW
Deemed / Contract Energy 242.65 GWh 
Wet Saleable Energy204.894 GWh
Dry Saleable Energy37.756 GWh
Construction Time and Key dates 
Development and Construction Time Power1 year (access road) + 3 years
Purchase Agreement with NEA February 09, 2017 (Magh 27, 2073)
Generation license issued date and validityMarch 30, 2017 (Chaitra 17, 2073) 35 years
Required Commercial Operation Date (RCOD)June 11, 2021 (Jestha 28, 2078)
Revised RCOD August 16, 2033 (Bhadra 1, 2079)

**Note:

  •  These salient features are based on the DPR report of Palun Khola Small Hydropower Project Prepared by HCE.
  •  Salient features of all alternatives are presented in Chapter 15 of this report.
Scroll to Top